Vermont Public is independent, community-supported media, serving Vermont with trusted, relevant and essential information. We share stories that bring people together, from every corner of our region. New to Vermont Public? Start here.

© 2024 Vermont Public | 365 Troy Ave. Colchester, VT 05446

Public Files:
WVTI · WOXM · WVBA · WVNK · WVTQ · WVTX
WVPR · WRVT · WOXR · WNCH · WVPA
WVPS · WVXR · WETK · WVTB · WVER
WVER-FM · WVLR-FM · WBTN-FM

For assistance accessing our public files, please contact hello@vermontpublic.org or call 802-655-9451.
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

Explore our latest coverage of environmental issues, climate change and more.

Windham Wind Developers Report Preliminary Findings

Residents of Windham packed the local meeting house on Tuesday night to hear about the findings of three wind test towers on the ridge between Windham and Grafton. The towers were erected last spring to determine the feasibility of a commercial wind project in the two towns. But the would-be developers say it’s too soon to reach any conclusions.

The test towers were built by the Spanish Energy conglomerate Iberdrola Renewables. But Meadowsend Timberland Limited of New London, NH,  also known as MTL, is the driving force behind the project.  

The company is the town's largest landowner. It also owns most of the Northeast Kingdom land where Sheffield Wind was built in 2011. MTL co-owner Jamey French says the firm is family-owned, environmentally concerned and dedicated to preserving working forest land.

“We, Meadowsend Timberland, our family, were the ones who asked Iberdrola to investigate the options for wind on this property," French said. "We had a success with the property up in Sheffield. It worked well. We are proud of it. I also want to state right up front that it’s very important for everybody here to know that we are very much in charge of this process and the final decisions around it, and the final decisions will be made by us.”

French told the gathering it will likely take two or three years to collect the data necessary to make that call. Construction wouldn’t start until 2019, assuming the project proves viable and receives state approval.

Don Hammond, Iberdrola’s regional engineer, said most of the findings have been positive.

“We think the wind is there,” Hammond said. “The average wind speeds look promising. But we found turbulence in the wind stream. The terrain is complex -- and turbulence and wind turbines don’t necessarily go well together.”

Until more is understood about the site, Hammond said, it isn’t possible to say what size the turbines will be, or exactly where they would be located.

"We think that, assuming we can answer the questions as far as the turbulence and the character of the wind, and depending on the size, it could be 15 turbines," Hammond said. "It could be 30.”

In 2008, after battling a wind proposal that didn’t go forward, Windham amended its town plan to prohibit commercial wind within the town borders. Local officials were quick to oppose the current proposal. Organizers of Tuesday’s meeting said they hoped to spark a town-wide dialogue that considers all sides of the issue.

One resident asked if Meadowsend would try to build the project even if the town opposed it. Jamey French, the company co-owner, didn’t have an immediate answer.

Susan Keese was VPR's southern Vermont reporter, based at the VPR studio in Manchester at Burr & Burton Academy. After many years as a print journalist and magazine writer, Susan started producing stories for VPR in 2002. From 2007-2009, she worked as a producer, helping to launch the noontime show Vermont Edition. Susan has won numerous journalism awards, including two regional Edward R. Murrow Awards for her reporting on VPR. She wrote a column for the Sunday Rutland Herald and Barre-Montpelier Times Argus. Her work has appeared in Vermont Life, the Boston Globe Magazine, The New York Times and other publications, as well as on NPR.